Change Order Calculator

A change order is the one piece of paper that turns extra work into money you can collect. This calculator does the arithmetic on the back of it: the original contract, the changes that are actually signed, and the revised total the customer owes against now. Priced but unagreed work stays in its own column, because that work is not money yet.

Type in the numbers. You will get the revised contract total, the change as a share of the job, the point where your own threshold says another signature is needed, what retainage holds back, and what is left to bill. Free, no email, runs right on this page.

The signed number, before any changes. What the customer agreed to at the start.

Every change you and the customer both signed, added up. This is the only money that counts toward the revised contract total.

A change order can take work away as well as add it. Pick credit back and the revised contract drops by the amount.

Extra work you have priced and talked about, with nothing on paper. Leave it at 0 if there is none. Get it in writing before the crew starts, and it moves into the field above.

A change order can take work away as well as add it. Pick credit back and the revised contract drops by the amount.

What you have already invoiced on this job, including progress payments. What is left to bill is the revised contract minus this.

The share the customer holds back until the job is done. Leave it at 0 if this job has none. Retainage is withheld against the revised contract, so a signed change gets held back too.

The share of the original contract that needs a fresh signature before the change is agreed. Ten percent is the common contract term. Set it to whatever your own agreement says, because this number is yours and not ours.

$1,850 of work is priced but not signed. It is not in the revised contract below, because nobody has agreed to pay for it yet. Get it in writing before the crew starts.

Revised contract total

$52,700

Original contract plus signed changes. Nothing unagreed is in here.

Signed changes are

8.7%

Sign the $1,850 you priced and the contract total goes to $54,550, or 12.5% of the original.

Your signature line sits at

$4,850

$650 of change left before you hit your own 10.0% line

Still to bill

$30,700

41.7% of the revised contract is already billed

Held back as retainage

$5,270

a share of the revised total, not just the original contract

Paid once retainage releases

$47,430

If the unagreed work gets signed

$54,550

12.5% of the original contract. Still not in the revised total above.

The Revised Contract Price

The revised contract price is the original contract plus every change order that has been signed, and nothing else. Not the change you priced on Tuesday. Not the one the customer said yes to in the driveway. The signed ones.

That is the rule the calculator applies, and it will not let you talk it out of the rule. Put a number in the unagreed field and it appears in its own tile with its own label, while the revised total above it does not move. It moves the day the signature lands, and until then it is a price, not a receivable.

A change order can also take work off the job. Pick credit back and the revised total drops, which is the honest answer when the owner removes a scope item. If you want the paperwork half of this, the free change order template has the signable form.

The number on this page is the one you can bill against.

A calculator tells you the revised total once, with the numbers you remembered. SiteOps builds the change order against the contract, gets the customer signature, and moves the revised contract price the moment that signature lands. The signed copy stays on the job record.

Sign It Before the Crew Starts

The expensive version of a change order is the one you write after the work is done. By then the extra is finished, the customer is comparing your invoice to a number they agreed to months ago, and what should have been a two minute signature becomes a conversation about what was included.

So the sequence matters more than the form. Notice the extra. Price it. Get the signature. Then start. A change order signed first is part of the contract and the crew hours on it are earning. Signed last, it is a request.

The Priced But Unagreed Column

The unagreed figure on this page is not a nag. It is the number that tells you how much work is already at risk on this job, and it is the same figure the calculator refuses to add to the revised contract until somebody signs.

Keep that number at zero and the job has no argument in it. Watch it climb and you know what the next hour of your week is for.

What SiteOps Does With It

The calculator prices one change order. The contract and change order tools in SiteOps build it against the contract. It carries the scope, the amount, and the effect on the completion date. The customer signs it in SiteOps, and the signed copy lands on the job record.

The revised contract price in the product is derived the same way this page derives it, the original plus the signed change orders, so nobody hand-edits the original to make the paperwork match. Invoices bill against that revised price, and the change counts as revenue in the daily profit and loss for the job. The crew hours on the extra land on the same job through GPS-verified clock-ins.

ONE JOB, AND THE NUMBERS THAT MOVE TOGETHER

Original contract
$48,500
Signed change orders
+ $4,200
Priced, not signed
$1,850 held out
Revised contract price
$52,700
Billed to date
$22,000 (41.7%)
Held as retainage
$5,270
Still to bill
$30,700

The revised contract price is worked out, never typed in. Add a signed change order and it moves. Add an unsigned one and it does not.

Want the signable page instead of the math?

The free one-page change order template has the scope, the amount, the revised contract price, the schedule effect, and the two signature lines. Drop your email and the PDF opens right away.

Frequently asked questions

How do I calculate a revised contract price with change orders?
Add every signed change order to the original contract. Additions increase it and credits reduce it. Leave out anything that has been priced but not signed, because an unagreed price is not part of the contract yet and billing against it is how a job ends up in an argument.
Does a change order have to be signed before the work starts?
For a covered California home improvement contract, yes. Business and Professions Code section 7159, which is published at leginfo.legislature.ca.gov, says a change to the contract must be in writing and signed by the parties before the changed work begins. Other contracts follow their own terms, so read yours and check with your attorney.
What is the difference between a change order and a new contract?
A change order changes a contract that already exists. It describes the added or removed work, the amount added to or subtracted from the price, and any effect on the schedule, and it becomes part of the original agreement. A new contract replaces the original, and most jobs never need one.
What percentage of a contract can be a change order?
There is no industry number, and anyone quoting one is guessing about your contract. What matters is the threshold in YOUR agreement, which is why the calculator takes it as an input and ships at 10 percent. Set it to whatever your own contract says, then watch it on each job.
Why is the unagreed work kept out of the revised contract total?
Because until the customer signs, nobody has agreed to pay for it. Adding it into the contract total flatters the job and hides the risk. Keeping it in its own figure shows you exactly how much priced work is sitting there unsigned, which is usually the number a contractor most needs to see.
Is retainage withheld from change orders too?
Usually yes. A signed change order becomes part of the contract, so the same retainage percentage applies to the higher revised total unless the change order says otherwise. That is why the last invoice on a job with a lot of changes is often smaller than the contractor expected.

This calculator and everything on this page are general information for contractors, not accounting, tax, or legal advice. Contract requirements, change order thresholds, and retainage rules differ by state, by owner, and by agreement, and a web page does not know yours. The defaults are editable examples, not industry benchmarks. Run your own contract past your attorney and your books past your CPA before you change how you price or bill work.

General information, not legal advice. Laws and exceptions change. Check the current California statute, CSLB guidance, and your attorney before relying on this.