Concrete Bid Calculator

Put in your slab size, your plant quote, your crew, and the margin you want to keep. You get a bid price, a per-square-foot check, and a breakdown of where the cost goes. It works as a concrete estimate calculator for flatwork: driveways, patios, garage slabs, and walks.

The defaults are a demo driveway, the same one from our concrete job costing post, so you can see the math before you type. Every dollar figure is a placeholder. The calculator is right below, with no signup and no email. If you have ever priced by concrete cost per square foot alone, the third section shows what that number hides.

Bid price

$11,201

[ Concrete ]

Length times width, in square feet. Add every pad, walk, and apron on the job together. This number also drives the per-square-foot check. 680 is the demo driveway.

Inches. Most residential flatwork is 4. Driveways that see trucks often run 5 or 6. Thickened edges, aprons, and curbs eat more than the flat math shows, so add them to your area or bump the waste.

Extra on top of the takeoff. 5 is a placeholder. Uneven subgrade, thickened edges, and curbs eat more than the flat math shows.

8.40 yd needed. Plus 5.0% waste is 8.81 yd. Order 9.00 yd, rounded up to the next quarter yard.

Filled in by the yardage helper. If your plant batches in half or whole yards, type that number here and the helper will stop overwriting it.

The per-yard number on your plant quote for the mix you are pouring. $185 is the demo placeholder, not a going rate. Put your quote in.

Whatever your plant bills on the ticket beyond the per-yard price: fuel surcharge, sales tax, wait time, any minimum-load charge. Add it here as one number, or fold it into the per-yard price. Not both.

[ Base, subs, and equipment ]

Everything that is not the mud: base rock, rebar or mesh, form lumber and stakes, expansion joint, cure and seal. Receipts, not memory. $585 is the demo number.

Tear-out and haul-off, grading, a finishing crew. Whatever you sub out, off their quotes. $1,100 is the demo haul-off sub.

The pump company invoice, if you need one. Type 0 if the truck can chute it. Your own placing and finishing labor is the crew line below, not here. $450 is the demo pump.

Saw, plate compactor, trowel machine, blades, fuel, dump fees, permit. Direct job costs that are not labor, materials, or subs. $380 is the demo saw and compactor rental.

[ Crew ]

How many men on the job. Count yourself if you are on the tools. A part-timer can be 0.5.

Hours each man will put in over the whole job: form, pour, finish, strip. If pour day brings extra finishers, use total man-hours divided by crew size. 16 is the demo's two-day job.

Crew hours on the job: 64

What an hour of labor really costs you: wage plus payroll taxes, comp, insurance, and time off. Not what you bill and not the bare wage. Open the burden helper if you want it built for you. $39.20 is the demo math.

The job's share of the shop, trucks, insurance, and office, charged per crew hour. Find yours: a year of overhead divided by the field hours you charge to jobs, not every paid hour. A per-hour rate recovers nothing on material and subs. If your work is material heavy, the percent-of-cost method in the job costing calculator fits better. $18 is the demo number.

[ Your margin ]

The share of the price you keep. Overhead is already in your cost above, so this is what you keep after overhead. If your usual number is meant to cover overhead too, use a smaller one here. 30 is the demo math, not advice.

Bid price

$11,201

Total job cost

$7,841

Profit at that price

$3,360

Bid per sq ft, everything in

$16.47

Bid price divided by slab area. Every cost line above plus margin.

30.0% margin is a 42.9% markup on cost. Why they differ.

Where the cost goes

Concrete, delivered$1,665 (21.2%)
Base, rebar, forms, cure$585 (7.5%)
Subs$1,100 (14.0%)
Pump$450 (5.7%)
Equipment and rentals$380 (4.8%)
Crew labor$2,509 (32.0%)
Overhead$1,152 (14.7%)

How a Concrete Bid Builds

A concrete bid is cost plus margin, and the cost has seven lines. Concrete as delivered, with whatever the plant bills on the ticket. Base, rebar, forms, and cure. Subs, like tear-out and haul-off. The pump. Equipment and rentals. Crew labor at the loaded rate, not the bare wage. And a share of overhead, charged per crew hour.

Add those up and you have the cost. Then divide by one minus your margin. Do not multiply. A 30% margin means the price is cost divided by 0.70, which is a 42.9% markup on cost. The demo driveway costs $7,841 and bids at $11,201. Our concrete job costing post priced the same job at $11,200, which is this number rounded to the hundred.

Skip a line and the bid looks fine until the job is over. A ContractorTalk poster who lost a driveway to a much lower bid in 2014 worked it backward: “The materials cost, permit and my insurance barely cover that, most of my crews labor (not including my labor) put me way over that, how can this be?” (typo his). The likely answer is that the low bidder never added up the same seven lines.

How to Calculate Concrete Yardage

Concrete yardage is area times thickness, in cubic yards. Take square feet, multiply by thickness in feet, and divide by 27. A 680 square foot driveway at 4 inches is 680 × 4 ÷ 12 ÷ 27, about 8.40 yards. Add waste, then round up to what the plant will batch. The calculator adds 5% and rounds up to the next quarter yard, which makes the demo order 9 yards.

Order tight and the short load costs more than the extra yard would have. A Breaktime regular said it plainly in 2006: “if you run short and have to order a 1/4 more, its a two yard minimum” (typo his). A 2009 Heavy Equipment Forums thread on figuring concrete by the yard gave the same warning: “partial load charges will kill your wallet quick.” His plant had a five yard minimum and a $50 partial charge, at 2009 prices.

These are line items contractors report, not universal constants. The demo order of 9 yards clears the minimums those posters name, which is why its truck fees sit at $0. If your plant bills a fuel surcharge, tax, or wait time, put it in the truck fees field. Then it lands on the job, priced in advance.

The bid is the plan. SiteOps shows you the pour.

This calculator prices the job before the truck rolls. SiteOps tracks what the job is making while it runs: labor from GPS-verified clock-ins, receipts as they are scanned, and a daily P&L per job. The margin you planned here becomes a number you watch, not a number you hope for.

Want to see every free calculator? Browse the full tools index.

Concrete Price per Square Foot

Divide the bid by the slab area and you get the per-foot number. The demo is $11,201 over 680 square feet, or $16.47 per square foot, everything in. That is a check, not a starting point. Build the bid from cost first, then look at the foot price to see if it passes the smell test in your market.

Plenty of the per-foot numbers you hear leave something out, and the thread rarely says what. A 2010 ContractorTalk thread reported a rival doing builder flatwork at $2.50 a foot, concrete and rebar included, at 2010 prices. A South Dakota contractor answered that he “wouldn't dream of pouring for $2.50 but I know contractors who do.” Compare a turnkey foot only to a turnkey foot. A tear-out driveway with base, a pump, and haul-off is a different product from a builder slab on prepared grade.

The per-foot habit is also how scope gets missed. An excavation owner on Heavy Equipment Forums looked back in 2021: “Underbid many jobs, some jobs I didn't realize what was required and customers refused to pay extra so I lost.” Then: “It hurts loosing money on jobs though” (typo his). A line-by-line bid catches what a foot price hides. When the job is done, run the real numbers through the construction profit margin calculator to see what you kept.

Two Lines That Hide in a Bid

The two lines concrete bids skip most are labor burden and overhead. Burden is what rides on top of the wage: payroll taxes, workers comp, liability insurance, time off. Comp on concrete crews tends to run steep. Overhead is the shop, the trucks, the insurance, and the office, and every job has to carry a piece of it. The burden math is in our complete guide to construction job costing. The full list of what belongs in a job cost is in How to Calculate Construction Job Costs.

On the demo driveway, wages alone and no overhead feel like $5,972 of cost. The real cost is $7,841. The gap is $717 of burden and $1,152 of overhead. Price the felt number for a 30% margin and you sell the job for $8,531, which leaves an 8.1% margin after the real cost. Nothing went wrong on that job. The math was short two lines.

A Heavy Equipment Forums owner put the overhead half in one line in January 2026: “Now with slow years that 20% markup does not cover all the over head expenses and I have to eat it out of my wages” (typo his). This calculator charges overhead per crew hour. A per-hour rate recovers nothing on material and subs. If your work is material heavy, the percent-of-cost method in the construction job costing calculator fits better. Either way, put the line in before you bid, not after.

The Bid Is the Plan

The number you just ran is the plan on the day you send it. Then the pour happens. The subgrade fights back and the crew runs 12 hours over. On the demo, that takes the cost to $8,527 and the margin at the sold price to 23.9%. Nobody sees that on pour day unless the hours land on the job the day they happen.

One owner on Heavy Equipment Forums said in 2022 that his problem was “keeping track of my employee's time, my time, and what we are doing when, and for what job.” That is the gap SiteOps fills. Crews clock in with GPS at the slab, and the hours land on that job the same day. A daily P&L per job shows what the pour is making. See how SiteOps tracks job costs while the job is running, starting with GPS-verified time tracking that puts real hours on the right job.

[ Free download ]

Get the job costing spreadsheet

A ready-made budget vs actual tracker with the burden and overhead math built in. Drop your email and it opens right away. We might follow up once to ask if it helped. No lists, no spam.

Frequently asked questions

How many yards of concrete do I need?
Multiply the slab area in square feet by the thickness in feet, then divide by 27. A 680 square foot slab at 4 inches needs about 8.4 cubic yards before waste. Add waste for uneven subgrade and thickened edges, then round up to what your plant will batch. The yardage helper in the calculator does this for you.
How many square feet does a yard of concrete cover?
About 81 square feet at 4 inches thick, 65 at 5 inches, and 54 at 6 inches. That is 27 cubic feet divided by the thickness in feet. Use it as a quick check on a takeoff, not as the order. A 680 square foot slab at 4 inches needs 8.4 yards before waste.
How much waste should I add when ordering concrete?
There is no universal number. The calculator starts at 5 percent as a placeholder. Uneven subgrade, thickened edges, and hand-formed curbs eat more than the flat math shows. Running short usually costs more than ordering heavy, because a make-up load can carry a minimum charge and the crew waits on it.
What goes into a concrete bid?
Seven cost lines, then margin. Concrete as delivered, including any delivery charges your suppliers bill. Base, rebar, forms, and cure. Subs such as tear-out and haul-off. Pump. Equipment and rentals. Crew labor at the loaded rate, not the bare wage. A share of overhead. Add them up, then divide by one minus your target margin to get the bid price.
What is a good profit margin for concrete work?
No single number fits every shop. Margin has to cover the profit you are in business to make. This calculator already puts overhead in the cost, so the margin here is what you keep after overhead. The 30 percent default is demo math, not advice. Work from your own costs and your own books.
How much should I charge per square foot for concrete?
Build the bid from your costs first, then divide by the slab area to get your per-foot number. The demo driveway works out to $16.47 per square foot with tear-out, base, concrete, pump, overhead, and margin included. Compare that only to other turnkey prices. Many per-foot numbers you hear leave out lines like tear-out, base, or the pump, so ask what a foot price covers before you compare.

This calculator and page are general information for the construction trades, not accounting, tax, or legal advice. The tool does not know your plant, your market, your comp rate, or your books. Nothing here is a recommendation of what to charge on any specific job. Quoted forum prices are the posters' own from their stated years. Talk to your accountant before changing how you price work.