The long dimension of the pour, in feet.
The other dimension, in feet. For an L shape, split it into two rectangles and add the yards.
Depth in inches. 4 is a standard driveway or walkway on prepared subgrade; 5 to 6 for a slab that carries a vehicle. Below an inch is not a slab, and above two feet needs an engineer's drawing rather than a calculator.
Five percent on flatwork over subgrade you prepared yourself. Ten when the subgrade is rough, the slab has thickened edges or a turned-down perimeter, the forms were set by hand, or the pour has to finish in one pass with no cold joint allowed.
How that was worked out
- Area
- 20 × 30 = 600 sq ft
- Thickness in feet
- 4 in ÷ 12 = 0.333 ft
- Cubic feet
- 200 cu ft
- Divide by 27
- 7.4 cu yd
- Plus 5% waste
- 7.8 cu yd
- Rounded up to the quarter yard
- 8 cu yd
Order this many yards
8
Waste and the quarter-yard round-up included. 7.4 cu yd before waste.
Slab area
600 sq ft
Volume
200 cu ft
60 lb bags
467
0.45 cu ft per bag
80 lb bags
350
0.60 cu ft per bag
One yard covers
81 sq ft
At 4 inches thick. 324 divided by the thickness.
The Formula
Concrete is ordered in cubic yards, and a cubic yard is a box three feet on every side. The formula is length in feet, times width in feet, times thickness in feet, divided by 27.
A 20 by 30 foot slab poured 4 inches thick is 600 square feet times one third of a foot, which is 200 cubic feet, which is 7.4 cubic yards. If you would rather not convert the thickness, square feet times thickness in inches divided by 324 is the same sum, because 324 is 27 times 12.
Waste, and Why It Matters
Nobody pours the drawing. The subgrade is never perfectly flat, the slab runs a little thick where it meets the forms, concrete stays in the chute and the wheelbarrow, and the last yard of the truck is never quite the last yard. That is what the waste factor is for.
Five percent is the working number for flatwork over subgrade you prepared yourself. Ten is the honest number when any of these is true: the subgrade is rough or uneven, the slab has thickened edges or a turned-down perimeter, the forms were set by hand and the depth wanders, or the pour has to finish in one pass with no cold joint allowed.
Then round up to what the plant batches, which is usually a quarter yard. On the 20 by 30 slab, 5 percent waste takes 7.4 to 7.8 yards, and the quarter-yard round-up makes the order 8. That round-up is the reason to do this on paper rather than in your head at the counter.
Ordering Short Costs More
Running short mid-pour is the most expensive thing on this page. A short load means a second truck with its own minimum charge, or a cold joint where the first pour stopped, or a crew standing in wet concrete while the clock runs. Set against that, half a yard you did not strictly need is cheap.
The other direction has a trap of its own. An extra yard you cannot place is a pile that sets in the driveway and gets broken up on Monday, and the truck still billed you for it. Order to the waste factor and the batch size, not to the drawing and not to a guess.
Under about one yard, price the bags before you call the plant. A truck carries a minimum charge and a short-load fee that dwarf the material on a small pad, and the calculator gives you the bag count for both the 60 pound and the 80 pound mix.
Yardage Is Not the Bid
Yardage is the easy line to see and rarely the biggest one. On the demo driveway in our concrete job costing post, the delivered concrete is about 29 percent of the cost. The lines that get skipped are crew labor at the loaded rate and the job's share of overhead.
The concrete bid calculator carries the quantity from this page into those lines: delivered concrete, base, rebar, forms, pump, labor at the loaded rate, an overhead share, and the margin you want to keep. Get the quantity right here, then price the job on top of it there.
The pour is one cost line
You just worked out the concrete. The job also carries crew hours, material off the receipt pile, and the shop's overhead, and those are the lines that decide whether the pour made money. SiteOps puts all of it on one job page while the work is happening.
A Thickness Error Travels
A yardage error does not stay in the yardage. Every quantity downstream of the slab thickness moves with it: the base depth, the rebar grid, the form length, and the labor hours somebody estimated off the same wrong number. A pour figured at 4 inches and poured at 5 is 25 percent more concrete and 25 percent more mud to move, and neither the bid nor the crew was told.
Our how many yards of concrete do I need post walks the same formula in words, with the six questions we get asked most about thickness, waste and ordering.
Get the job costing spreadsheet
A ready-made budget vs actual tracker with the burden and overhead math built in. Drop your email and it opens right away. We might follow up once to ask if it helped. No lists, no spam.
Frequently asked questions
- What is the formula for cubic yards of concrete?
- Length in feet times width in feet times thickness in feet, divided by 27. A 20 by 30 foot slab at 4 inches is 600 square feet times one third of a foot, which is 200 cubic feet, which is 7.4 cubic yards.
- How many yards of concrete do I need for a 30 by 30 slab?
- At 4 inches it is 11.1 cubic yards before waste. With 5 percent waste it is 11.7, and most plants batch in quarter yards, so the order is 11.75 yards.
- How much waste should I add to a concrete order?
- Five percent is the working number for flatwork on prepared subgrade, and ten is safer when the subgrade is uneven, when there are thickened edges, or when the forms are hand set and the depth wanders. Then round up to the batch size.
- How many square feet does a yard of concrete cover?
- A cubic yard covers 324 square feet at one inch thick, 108 square feet at 3 inches, 81 square feet at 4 inches, and 54 square feet at 6 inches. Divide 324 by the thickness in inches and that is the coverage.
- Why did my concrete order come up short?
- Four causes, in order of how often they happen: the subgrade was not as flat as it looked, the slab was thicker than the drawing at the edges, the forms spread under the pour, and the waste factor was left at zero. Any one of them can eat half a yard on a small slab.
- Do I order concrete in yards or in meters?
- In the United States concrete is ordered in cubic yards and batched in quarter yards. Outside the US it is usually cubic meters, so convert at 1 cubic meter equals 1.308 cubic yards.
This calculator and page are general information for the construction trades, not engineering, accounting, tax, or legal advice. Structural slabs, footings and anything carrying a load need an engineer's drawing and a thickness you did not choose yourself. The tool does not know your plant, your market, or your batch size. Nothing here is a recommendation of what to order on any specific job.